Grant Line Road won’t be rocky much longer
by TP staff
Mar 21, 2011 | 3525 views | 9 9 comments | 10 10 recommendations | email to a friend | print
Cones and signs mark the roadway as drivers navigate the construction zone on Grant Line Road heading east from Parker Avenue.  Glenn Moore/Tracy Press
view slideshow (3 images)
When warmer weather arrives to stay, motorists will be greeted by a smoother ride on Grant Line Road.

According to city engineer Kul Sharma, the east-west artery in northern Tracy that’s been under construction for more than a year can’t be paved until the outside temperature is consistently above 65 degrees.

But as soon as the weather warms and work is finished on the street's south sidewalk, Sharma said, crews will grind down the existing bumpy street surface and lay down a new, 2½-inch thick layer of blacktop.

It will mark the final phase of a drawn-out effort to replace aging infrastructure beneath Grant Line Road, a project Sharma said was much-needed.

“Most of those lines are very old, and they are dysfunctional and we’ve had multiple repairs over there,” he said.

The water main, as well as sewage lines, water lines and storm drains, was replaced between Tracy Boulevard and MacArthur Drive.

One of the tricky parts of the project, the city engineer explained, was that the sewer and water lines between the main — which runs down the middle of the street — and businesses, homes and apartments lining the boulevard had to be dug up and replaced.

That partially accounts for the wheel-jarring state of the road, as crews had to continually dig up and patch the driving surface.

That’s drawn plenty of complaints from motorists jostled by the uneven pavement and confused by construction signs, as well as from nearby residents, who have complained about being without water, power and parking for stretches of time.

Other setbacks delayed the project’s completion date.

While digging out the crumbling infrastructure, crews found pipes and lines that weren’t on any schematic. And while an AT&T line and a Chevron gas main were identifiable, many were unclaimed, and Sharma said that excavators took significant time to determine what was in those pipes, if anything at all, out of an abundance of caution.

“The main problem was, when we were doing all those utility connections, there were conflicts with existing lines,” Sharma said.

But that’s all done, he said.

“The majority of the difficult work, the work which has conflicts, is all complete.”

All that’s left is some sidewalk construction on the south side of Grant Line Road, laying the asphalt and building a few landscape medians.

Sharma hopes it’ll be done as soon as April.

“Of course, weather permitting,” he said on a rainy Friday. “For example, today, we can’t have any work done.”

At a glance

• The Grant Line Road infrastructure replacement and repaving project, when all is said and done, will cost $5.2 million. It’s being paid for by county Measure K sales tax revenue, gas tax revenue and infill development fees

Comments
(9)
Comments-icon Post a Comment
tommybahama
|
March 22, 2011
@mnwild - I agree that this project has been quite inconvenient but what ever happened to getting all your contractors lined up in advance so there are no scheduling delays?

That way if they rupture an undocumented water line or breech a sewer line they have the contractor coming quickly to take care of it. It seems like this project has been over extended due to poor project management and a lack of proper scheduling.
2toots&imgone
|
March 21, 2011
mnwild your right every contractor is going to take heat from someone. But this job has been going on long enough! It has been over a year and they still do not have the sidewalks done yet. I've done underground and it was not to long ago the mazingo pulled there equipment out. I have done reconstructs in this town 10th st., Central, Holly! This project is draging along. Let's face it some companies just get the job done and some don't! And paving is not the end of this job. They got to raise the utilities, put the loops in and still strip it! April...more like May by the way this job is going!
mnwild
|
March 21, 2011
Does anyone remember reading these same comments during the 11th Street renovation project? I certainly do.

Would it have been better to throw caution to the wind and have the contractor rupture an undocumented gas line? Or how about replacing the sewer line, then repaving the street. Then in 6 months the water line, then repaving the street. Then..... (you get my drift). I worked for a Bay Area city for 18 years and listened to caller after caller with the same complaints I've been reading in these blogs and that was WITH Granite Construction as one of the contractors doing the work.

This project was inconvenient and hard on people and businesses, but it had to be done. Aging infrastructures must be replaced BEFORE something catastrophic happens (ie. San Bruno). Imagine the mess there would have been on Grant Line Road if the water main unexpectedly blew at 6 a.m. on a weekday. By the time the crews got to the site to shut off the water, there would be mud and debris washing down the street and possibly into businesses. The businesses connected to that line would be without water for an unknown, but extended period of time. All traffic would have to be diverted around the area, because an uncontrolled blown water main will leave a huge hole in the center of the street.

And imagine the monetary impact on the affected businesses if this happened over and over because projects like this one are not done or are done incompletely because City staff are worried about the "inconvenience" doing the job right will have. I frequented businesses on Grant Line Road during this construction and experienced everything complained about by others, but knowing how well the 11th Street project turned out, I choose to see the "glass half full" this time.
ConcernedParents
|
March 21, 2011
Not to mention the businesses that went under, like Carmen's. The Grantline project took (still taking) way too long, by any standards.
tommybahama
|
March 21, 2011
Another fine example of the kind of service we get from the city of tracy for this premium tax dollars we pay.

2toots&imgone
|
March 21, 2011
Would of been done already if Granite Construction had that job!

justmembj
|
March 20, 2011
Max24-well said. I couldn't agree more. It has been a complete nightmare driving on that stretch of road for entirely too long. I feel so bad for those residents that have endured the extra hassle of power outages and seeing that awful construction every time they leave their house.
Max24
|
March 20, 2011
I can believe the City has allowed the workmanship, lack of quality, safety and time that that contract has taken to complete the project. It would of been done much sooner if the City pushed them to finish, instead of allowing them to stop the forward progress so they could go do another job before they completed this on. I hope that that contractor is being charged LD's.

City of Tracy should hire LOCAL CONTRACTORS to due work in our town.
storkfmny
|
March 19, 2011
Bout freakin time!!


We encourage readers to share online comments in this forum, but please keep them respectful and constructive. This is not a space for personal attacks, libelous statements, profanity or racist slurs. Comments that stray from the topic of the story or are found to contain abusive language are subject to removal at the Press’ discretion, and the writer responsible will be subject to being blocked from making further comments and have their past comments deleted. Readers may report inappropriate comments by e-mailing the editor at tpnews@tracypress.com.